Effluent Wastewater Storage Tank: Federal assistance solves IVGID procrastination
After almost 10 years, IVGID was successful in obtaining a grant from the US Army Corps of Engineers (USACE) for 75% of the design and construction of the Wastewater Storage Tank. The estimated costs are $7,601,000 and IVGID will be responsible for $1,900,250. The grant was assembled from unused funds in the Section 595 program that other municipalities turned back to USACE. Final design will be completed shortly and environmental clearances are expected in October. A no-bid contract will be selected next May and construction is anticipated to be complete in October 2024. TRPA coverage costs remain an outstanding item. … Continue reading →